St. Lorenz Church, Hall Choir, construction phase Jakob Grimm Choir vault, pillars and arches

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm

from 1464 to 1477

Choir vault, pillars and arches


Construction of St. Lorenz Church began around 1250.

The late Gothic hall choir was completed in 1477, see description of the artist Jakob Grimm.

Location: Nuremberg, St. Lorenz Church

Design: Grimm, Jakob

photo 2011, Theo Noll

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm Central net

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm

from 1464 to 1477

Central net


Construction of St. Lorenz Church began around 1250.

The late Gothic hall choir was completed in 1477, see description of the artist Jakob Grimm.

Location: Nuremberg, St. Lorenz Church

Design: Grimm, Jakob

photo 2012, Theo Noll

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm Detail of the vault supports

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm

from 1464 to 1477

Detail of the vault supports


Construction of St. Lorenz Church began around 1250.

The late Gothic hall choir was completed in 1477, see description of the artist Jakob Grimm.

Location: Nuremberg, St. Lorenz Church

Design: Grimm, Jakob

photo 2011, Pablo de la Riestra

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm East bay of the choir ambulatory

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm

from 1464 to 1477

East bay of the choir ambulatory


Construction of St. Lorenz Church began around 1250.

The late Gothic hall choir was completed in 1477, see description of the artist Jakob Grimm.

Location: Nuremberg, St. Lorenz Church

Design: Grimm, Jakob

photo 2011, Pablo de la Riestra

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm Vault in the choir between the easternmost pair of pillars

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm

from 1464 to 1477

Vault in the choir between the easternmost pair of pillars


Construction of St. Lorenz Church began around 1250.

The late Gothic hall choir was completed in 1477, see description of the artist Jakob Grimm.

Location: Nuremberg, St. Lorenz Church

Design: Grimm, Jakob

photo 2012, Theo Noll

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm Vault in the choir between the easternmost pair of pillars with ambulatory breastwork

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm

from 1464 to 1477

Vault in the choir between the easternmost pair of pillars with ambulatory breastwork


Construction of St. Lorenz Church began around 1250.

The late Gothic hall choir was completed in 1477, see description of the artist Jakob Grimm.

Location: Nuremberg, St. Lorenz Church

Design: Grimm, Jakob

photo 2012, Theo Noll

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm Hall choir from southwest

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm

from 1464 to 1477

Hall choir from southwest


Construction of St. Lorenz Church began around 1250.

The late Gothic hall choir was completed in 1477, see description of the artist Jakob Grimm.

Location: Nuremberg, St. Lorenz Church

Design: Grimm, Jakob

photo 2011, Pablo de la Riestra

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm Onset of the arches at the inception of the choir

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm

from 1464 to 1477

Onset of the arches at the inception of the choir


Construction of St. Lorenz Church began around 1250.

The late Gothic hall choir was completed in 1477, see description of the artist Jakob Grimm.

Location: Nuremberg, St. Lorenz Church

Design: Grimm, Jakob

photo 2011, Pablo de la Riestra

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm Bays of the eastern ambulatory and central nave

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm

from 1464 to 1477

Bays of the eastern ambulatory and central nave


Construction of St. Lorenz Church began around 1250.

The late Gothic hall choir was completed in 1477, see description of the artist Jakob Grimm.

Location: Nuremberg, St. Lorenz Church

Design: Grimm, Jakob

photo 2011, Pablo de la Riestra

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm Vaults of the central nave

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm

from 1464 to 1477

Vaults of the central nave


Construction of St. Lorenz Church began around 1250.

The late Gothic hall choir was completed in 1477, see description of the artist Jakob Grimm.

Location: Nuremberg, St. Lorenz Church

Design: Grimm, Jakob

photo 2013, Theo Noll

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm West gable with arches (by Hans Behaim?)

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm

from 1464 to 1477

West gable with arches (by Hans Behaim?)


Construction of St. Lorenz Church began around 1250.

The late Gothic hall choir was completed in 1477, see description of the artist Jakob Grimm.

Location: Nuremberg, St. Lorenz Church

Design: Grimm, Jakob

photo 2006, Pablo de la Riestra

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm West gable with mullions and “hooks”

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm

from 1464 to 1477

West gable with mullions and “hooks”


Construction of St. Lorenz Church began around 1250.

The late Gothic hall choir was completed in 1477, see description of the artist Jakob Grimm.

Location: Nuremberg, St. Lorenz Church

Design: Grimm, Jakob

photo 2010, Pablo de la Riestra

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm West gable detail of the arches (by Hans Behaim?)

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm

from 1464 to 1477

West gable detail of the arches (by Hans Behaim?)


Construction of St. Lorenz Church began around 1250.

The late Gothic hall choir was completed in 1477, see description of the artist Jakob Grimm.

Location: Nuremberg, St. Lorenz Church

Design: Grimm, Jakob

photo 2010, Pablo de la Riestra

Jakob
Grimm

Further works

St. Lorenz Church, Hall Choir, construction phase Jakob Grimm
St. Lorenz Church, Hall Choir, construction phase Jakob Grimm

Menu

  • New
  • Search
  • Artists
  • Works of art
  • About us
  • Deutsche Version
  • Instagram

A project of the Förderverein Kulturhistorisches Museum Nürnberg e.V. (Association for the Promotion of the Museum of Cultural History Nuremberg - registered association)

The Förderverein Kulturhistorisches Museum Nürnberg e.V. supports the establishment of a museum of cultural history in Nuremberg. In anticipation of this it presents selected works of Nuremberg art in digital form. The Association will be happy to welcome new members. You will find a declaration of membership on our website.

Support us Feedback

Logo

© Protected under German copyright laws

  • Imprint
  • Privacy policy

Feedback

Please let us know your opinion about our website, the museum, our idea or any other evaluation. We shall be please about any comments and suggestions..